What are some of the benefits of using a network diagram Briefly discuss two and draw the network diagram below show and calculate the critical path.

List five attributes or characteristics of a project Manager and briefly discuss any two of the attributes and give reasons why each is important. (6marks).

What are some of the benefits of using a network diagram Briefly discuss two and draw the network diagram below show and calculate the critical path. (10 marks)

Tasks Preceding Time (weeks)
a              –         3
b             a        7
c             b          6
b           9
e            c           6
f            d           8
g ”        e,f”       10